Daily Field Report · Riverside restoration
East Wing — Tuesday, September 8
Prepared by M. Ortiz, project manager. Weather clear, 71°F.
Crew 4Hours 07:10–15:40Photos 14
1. Work completed
Framing on the east wing is complete. Drywall delivery staged on Level 2 (Fig. 1).
2. Site observations
Moisture noted at the north wall, reading 22% at 14:10. Drying to be confirmed before close-up (Fig. 2).
3. Time and materials
| Labor | 6 hrs |
| Drywall, 4×8 | 12 sheets |
| Dehumidifier | 1 day |
Fig. 1 — East wing framing, 09:32
Fig. 2 — North wall reading, 14:10